Day 288: On Feb 10th of the home improvement project drywall
work continued. Kevin applied mud at locations throughout
the basement. Phil lined the window wells with drywall and
corner bead. That's the last of drywall installation. Now it's
just mudding and then sanding. The mud needs to dry a day.
Kevin will be back tomorrow to put on a second coat. I'm frustrated with one of my time lapse cameras. I've had trouble with it in the past and then it works fine for a long stretch before messing up again. It stopped all on its own again a little after 10 AM so I missed almost everything that was done in the bedroom. I'll have to keep an eye on it again in the future. |