This project has been going on for many years. The big push was in 2010
when a new bathroom was built in the basement. That forced moving a
bunch of stuff around. This latest push was talked about for several
years and finally got its start on Nov 19th with a trip to IKEA to get
a wardrobe, book shelves, and a gate leg table. Two new Billy bookshelves
replaced two bookshelves in Joyce's "Room of Requirement". That started
a domino like reaction. Those two shelves went in the basement and
eveything in the old computer desk in the basement went on the shelves.
The desk was then given away. The wardrobe was put where the desk used
to be. There used to be six shelves arranged back-to-back dividing the
large open basement area in half. That was reduced to four shelves
back-to-back and a shorter shelf in place of a tall one. John's
computer desk was moved towards the wall opening up the area more.
There is still move to do.
|